- Mill Throughput - 30 mt/hr
 
- Plantation Area - 5,000 ha
 - Fresh Fruit Bunch (25 mt/ha) - 125,000 mt/year
 
- Operating on 24 hours per day - 19.97 mt/hr
 - Operating on 20 hours per day - 23.96 mt/hr
 - Operating on 16 hours per day - 29.95 mt/hr
 
- Production of CPO per year (22%) - 27,500 mt
 - Production of PK per year (5%) - 6,250 mt
 
- Management & Staff - 6 persons
 - Manpower requirements - 30 person / per shift
 - Total manpower - 96 persons / 3 shifts
 
- Water requirements - 60 m3/hour
 - Electrical power requirements - 900 KW
 - Mill & Appurtenance - 6 ha
 - Effluents ponds - 6 ha
 - Project time schedule - 20 months
 
Source - Perunding AME